By Hugo Melo
Author 1
Author 2
Author 3
Author 4
In 2008, this copper project began in Chile at the pre-feasibility level. During the study, 26 alternative options were developed and evaluated in terms of the production rate of the expansion, underground and open-pit alternatives, process plant locations, associated infrastructure and impacts of the 70km-long tunnels in the project schedule. SRK carried out a quantitative risk analysis of all the options and their impact on the economic model. The preferred option was taken forward to another engineering stage.